Menikah dengan Tri Sumiasih pada tanggal 21 Oktober 2012, dan telah di anugerahi seorang putri bernama Athiyah Hafizah Gendis Irawan
NO | Judul | Jumlah | Satuan | Nilai | TOTAL (RP) |
---|---|---|---|---|---|
1 | Pengukuran dan pemasangan Bouwplank | 118 | m | 78.500 | 9.263.000 |
2 | Direksi keet | 15 | m² | 1.050.000 | 15.750.000 |
3 | Mobilisasi | 1 | Ls | 17.500.000 | 17.500.000 |
4 | Pekerjaan tanah (galian tanah) | 31. | m³ | 95.000 | 3.017.200 |
5 | Pekerjaan tanah (urugan kembali) | 16. | m³ | 27.500 | 457.600 |
6 | Pile Cap (Beton K-350) | 9.6 | m³ | 1.750.000 | 16.852.500 |
7 | Pile Cap (Tulangan U-39) | 105 | kg | 15.670 | 16.590.613 |
8 | Pile Cap (Bekisting) | 86. | m² | 195.000 | 16.892.850 |
9 | PC Mine Pile Segitiga (300x300x300)mm | 770 | m | 450.000 | 346.500.000 |
10 | Cute of pile head | 29. | ea | 145.000 | 4.313.750 |
11 | Sloof beton (Beton K-350) | 26. | m³ | 1.750.000 | 46.200.000 |
12 | Sloof beton (Tulangan U-39) | 257 | kg | 15.670 | 40.334.580 |
13 | Sloof beton (Bekisting) | 237 | m² | 195.000 | 46.332.000 |
14 | Kolom 450x450 (beton k-350) | 52. | m³ | 1.750.000 | 91.997.500 |
15 | Kolom 450x450 (tulangan U-39) | 709 | kg | 15.670 | 111.207.169 |
16 | Kolom 450x450 (bekisting) | 473 | m² | 228.000 | 107.871.360 |
17 | Balok induk 600x300 (Beton K-350) | 151 | m³ | 1.750.000 | 264.600.000 |
18 | Balok induk 600x300 (Tulangan U-39) | 173 | kg | 15.670 | 272.469.960 |
19 | Balok induk 600x300 (Bekisting) | 136 | m² | 228.000 | 310.262.400 |
20 | Balok anak 400x200 (Beton K-350) | 53. | m³ | 1.750.000 | 93.240.000 |
21 | Balok anak 400x200 (Tulangan U-39) | 612 | kg | 15.670 | 96.013.224 |
22 | Balok anak 400x200 (Bekisting) | 479 | m² | 228.000 | 109.330.560 |
23 | Concrete slab S1 T=120mm (Beton K-350) | 108 | m³ | 1.750.000 | 189.000.000 |
24 | Concrete slab S1 T=120mm (Tulangan U-39) | 124 | kg | 15.670 | 194.621.400 |
25 | Concrete slab S1 T=120mm (Bekisting) | 972 | m² | 228.000 | 221.616.000 |
26 | Lena concrete t=50mm | 292 | m³ | 956.000 | 279.630.000 |
27 | Kuda-kuda, kayu | 575 | m² | 475.000 | 273.125.000 |
28 | Gording, Kayu | 225 | m² | 475.000 | 106.875.000 |
29 | Penutup atap, metal roof | 450 | m² | 250.000 | 112.500.000 |
30 | Pasangan Bata | 127 | m² | 37.500 | 47.790.000 |
31 | Plesteran | 254 | m² | 55.500 | 141.458.400 |
32 | Beton K-350 | 8.9 | m³ | 1.750.000 | 15.592.500 |
33 | Tulangan U-39 | 850 | kg | 15.670 | 13.328.119 |
34 | Bekisting | 80. | m² | 228.000 | 18.276.480 |
Total Biaya | 3.650.809.164 |